Activity

Immediate Predecessor(s)

Time (days)

A

2

B

6

C

1

D

B

10

E

A, D

5

F

C

6

G

E, F

10

This exercise contains only parts b, c, and d.Part 2b) The critical activities for the leadership training program development project are

B - D - E - G

.

c) The project length for the leadership training program development project =

?

days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!