Question: roject Cost Table Item Description: Cost Cost Details Workers Compensation Insurance $ 1 1 6 Per worker Training $ 2 , 7 3 0 Per

roject Cost Table
Item Description: Cost Cost Details
Workers Compensation Insurance $116 Per worker
Training $2,730 Per training session
Project Manager $3,000 Per week
Signs $45 Per sign
Permits $115 Per permit
Architect / Designer $75 Per hour
This is a risk opportunity. Calculate the EMV duration in days. For this risk, assume an experienced project manager is available and would need 20 days less for project planning and the building department has expanded and permits are now taking 15 days less than expected to process.