Question: uestion 1 0 ( 1 point ) Project Cost Table Item Description: Cost Cost Details Workers Compensation Insurance $ 1 6 3 Per worker Training

uestion 10(1 point)
Project Cost Table
Item Description: Cost Cost Details
Workers Compensation Insurance $163 Per worker
Training $3,528 Per training session
Project Manager $3,000 Per week
Signs $45 Per sign
Permits $115 Per permit
Architect / Designer $75 Per hour
This question is worth 2 points. Calculate the EMV based on the information available. The probability for this risk threat is 65%. Assume the project manager will need to purchase Workers Compensation Insurance for 13 workers and there will be a need for 4 training sessions.
Remember to add the minus (-) for answers with negative values.
Do not include $ sign or decimals in your answers.
Do not use a comma (,) to separate thousands.
Your Answer:
Question 10 options:
Answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!