Question: Rough-Cut Capacity Planning 1) If your operation has a total of 275,000 hours of labor available is it feasible to meet the following demand? Labor
Rough-Cut Capacity Planning
1) If your operation has a total of 275,000 hours of labor available is it feasible to meet the following demand?
Labor required = (Units Demanded x Standard Hours)
Product Units Demanded Standard Hours Labor required
(in hours/unit)
A 25000 0.4 10000
B 14500 1.1 15950
C 11500 0.2 2300
Total labor required: _____
Total labor available: 27500
Not feasible or feasible?
2) If your operation has a total of 65,000 hours of labor available is it feasible to meet the following demand?
Labor required = (Units Demanded x Standard Hours)
Product Units Demanded Standard Hours Labor required
(in hours/unit)
A 32500 0.6 19500
B 23000 0.8 18400
C 40000 0.2 8000
D 15000 1.15 17250
Total labor required: _____
Total labor available: 65000
Not feasible or feasible?
3) If your operation has a total of 75,000 hours of labor available is it feasible to meet the following demand?
Labor required = (Units Demanded x Standard Hours)
Product Units Demanded Standard Hours Labor required
(in hours/unit)
A 8000 1.2 9600
B 21000 1.5 31500
C 7000 0.3 2100
D 30000 0.95 28500
Total labor required: ______
Total labor available: 75000
Not feasible or feasible?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts