Question: RUNNING HEAD: Unit 7: Application Assignment 3 Chapter 13 Questions 4. Given the following data, perform a critical path analysis in excel to determine the


RUNNING HEAD: Unit 7: Application Assignment 3 Chapter 13 Questions 4. Given the following data, perform a critical path analysis in excel to determine the project's critical path. Your spreadsheet should indicate the early start schedule, late start schedule, and slack. Activity Duration Predecessors A 3 weeks B 15 weeks A C 5 weeks B D 3 weeks C E 6 weeks B F 4 weeks E G 2 weeks D.F 5. Draw a network diagram for the project described in question 4 8. Use Excel to create a Gantt chart of the project given in question 4