Question: 4. Given the following data, perform a critical path analysis in Excel to determine the projects critical path. Your spreadsheet should indicate the early start
4. Given the following data, perform a critical path analysis in Excel to determine the project’s critical path. Your spreadsheet should indicate the early start schedule, late start schedule, and slack.
Using the provided data values for minimum expected activity durations and maximum expected activity durations, use Excel to provide a PERT analysis of the project given in question 4. Include all calculations demonstrated
Activity Minimum Duration Maximum Duration A 2 4 12 18 C 3 D 2 4 E 4 8 F 3 1 3
Step by Step Solution
There are 3 Steps involved in it
A explained s... View full answer
Get step-by-step solutions from verified subject matter experts
