Question: Samuel is approximating project time and cost for building a new warehouse by multiplying the total square footage by a given dollar amount. Which of
Samuel is approximating project time and cost for building a new warehouse by multiplying the total square footage by a given dollar amount. Which of the following methods is he using?
Learning curves
Function point method
Ratio method
Consensus method