Question: Sansa is trying to complete a resource loading chart. At one step, both activity 8 & activity 9 are ready to be loaded but there
Sansa is trying to complete a resource loading chart. At one step, both activity 8 & activity 9 are ready to be loaded but there aren't enough resources to carry out both activities at the same time. Activity 8 is critical and has a duration of 5 days. Activity 9 has 2 days of slack and a duration of 2 days. What should Sansa do?
Select one:
A. Select either one of the two activities
B. Select Activity 8 first
C. Consult with her direct manager
D. Select Activity 9 first
E. Consult with her project team members