Question: Sansa is trying to complete a resource loading chart. At one step, both activity 8 & activity 9 are ready to be loaded but there

Sansa is trying to complete a resource loading chart. At one step, both activity 8 & activity 9 are ready to be loaded but there aren't enough resources to carry out both activities at the same time. Activity 8 is critical and has a duration of 5 days. Activity 9 has 2 days of slack and a duration of 2 days. What should Sansa do?

Select one:

A. Select either one of the two activities

B. Select Activity 8 first

C. Consult with her direct manager

D. Select Activity 9 first

E. Consult with her project team members