Question: Sansa is trying to complete a resource loading chart. At one step, both activity 8 & activity 9 are ready to be loaded but there

Sansa is trying to complete a resource loading
Sansa is trying to complete a resource loading chart. At one step, both activity 8 & activity 9 are ready to be loaded but there aren't enough resources to carry out both activities at the same time. Activity 8 is critical and has a duration of 5 days. Activity 9 has 2 days of slack and a duration of 2 days. What should Sansa do? Select one: A. Consult with her project team members B. Select Activity 8 first C. Select Activity 9 first D. Consult with her direct manager E. Select either one of the two activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!