Question: Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most
Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most likely estimation is 14 weeks, and the estimation that considers all the risks is 17 weeks.
Calculate the time estimation for Saras task. Use PERT for your calculation. (5 marks)
(4 marks for working, 1 mark for time estimate)