Question: Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most

Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most likely estimation is 14 weeks, and the estimation that considers all the risks is 17 weeks.

Calculate the time estimation for Sara’s task. Use PERT for your calculation.