Question: Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most
Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most likely estimation is 14 weeks, and the estimation that considers all the risks is 17 weeks.
Calculate the time estimation for Sara’s task. Use PERT for your calculation.
Step by Step Solution
3.41 Rating (154 Votes )
There are 3 Steps involved in it
PERT Program Evaluation Review Technique Time estimation ... View full answer