Question: Saved Help Save & Exit Submi Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,600
Saved Help Save & Exit Submi Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,600 of direct materials and used $4,100 of direct labor. The job was not finished by the end of September, but needed an additional $3,100 of direct materials and additional direct labor of $6,600 to finish the job in October. The company applies overhead at the end of each month at a rate of 150% of the direct labor cost incurred. What is the total cost of the job when it is completed in October? Multiple Choice $16,400 $19,600 $23,700 on 4