Question: Saved Help Save & Exit Submit A project is expected to provide cash flows of $10,800, $11,700, $14,800, and $9,300 over the next four years,

 Saved Help Save & Exit Submit A project is expected to

Saved Help Save & Exit Submit A project is expected to provide cash flows of $10,800, $11,700, $14,800, and $9,300 over the next four years, respectively. At a required return of 9.1 percent, the project has a profitability index of 1.355. For this to be true, what is the project's cost at Time O? . Multiple Choice $27,815 Insufficient information $43,409 525,497