Scaffolding is to be constructed on a wall of a three-story building in order for masonry rehabilitation
Fantastic news! We've Found the answer you've been seeking!
Question:
are effectively working 6-hours in an 8-hour day (subtracting 1 Hr for lunch and .5 hours each for setup and breakdown) are assigned to do the entire scaffolding erection, what duration
(in working days) should be used to schedule this activity? Round up your answer to the nearest
whole integer day. Q1.2 What is the Production Rate in SY/Hr to keep the crew productive for a minimum of 6 hours per day? Dont forget to convert!