Question: Scenario B: Consider the following generic manufacturing process. Throughput capacities are listed in parentheses after the name of each activity. Each task is performed by
Scenario B:
Consider the following generic manufacturing process. Throughput capacities are listed in parentheses after the name of each activity. Each task is performed by a separate piece of equipment.
There is an inventory buffer between each station, and assume there is no limit on how big the inventory buffer can become. Suppose the process starts with all buffers being empty. Task A (8 units/hr) ----> (Inventory buffer) ---> Task B (12 units/hr) ----> (inventory buffer) ---> Task C (4 units/hr) -----> (inventory buffer) ----> Task D (7 units/hr) Which task(s) would be starved? Pick all that apply (2 pts
A
B
C
D
NONE OF THE ABOVE
Refer to Scenario B. Which task(s) would be blocked? Pick all that apply (2 pts)
A
B
C
D
NONE OF THE ABOVE
What would Task A's utilization be? Pick the closest answer
20%
40%
60%
80%
100%
What would task D's utilization be? Pick the closest answer.
20%
40%
60%
80%
100%