Question: Scenario B: Suppose you are given the process flowchart shown below. temp.jpg . No buffer space between stations, so upstream tasks must wait if downstream

Scenario B:
Suppose you are given the process flowchart shown below.
temp.jpg.
No buffer space between stations, so upstream tasks must wait if downstream task is busy or if downstream task is unable to start processing immediately
Task 4 is an assembly stage - it requires 1 unit from task 2 AND one unit from Task 3 in order to do its work.
Each task can process 1 unit at a time
Which task(s) would be starved? Check all that apply.

Step by Step Solution

There are 3 Steps involved in it