Question: Scenario B:Suppose you have a four - activity sequential process. Throughput capacities in units per minute are shown in parentheses: Task 1 ( 3 )

Scenario B:Suppose you have a four-activity sequential process. Throughput capacities in units per minute are shown in parentheses:Task 1(3)---> Task 2(4)---> Task 3(2)---> Task 4(5).No buffers exist between tasks, so an upstream task must wait if the downstream task is busy.What is the actual throughput rate for the sequential process as a whole (i.e., at what rate would units exit task 4)? Pick the closest answer.
.5
1
2
3
4
5
Refer to Scenario B:If the process were to operate as described above, what would task 1's utilization be? Pick the closest answer.
0%
20%
40%
60%
80%
100%
Suppose you have a two-activity sequential process: Task 1---> Task 2.Task 1 has a throughput capacity of 10 units per hour; task 2 has a throughput capacity of 15 units per hour. There are no inventory buffers between tasks, so blocking may occur.Which of the following would be true?
Task 1 would encounter blocking
Task 2 would encounter blocking
Task 1 would encounter starvation
Task 2 would encounter starvation
Which of the following sequences best aligns with the six sigma process improvement model?
Construct flowchart --> Perform Time Study --> Capacity Analysis
Capacity Analysis --> Perform Time Study --> Construct Flowchart
Capacity Analysis --> Construct Flowchart --> Perform Time study
Construct flowchart --> Capacity Analysis --> Perform Time Study

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!