Question: 27) Scenario B: Suppose you have a four-activity sequential process. Throughput capacities in units per minute are shown in parentheses: Task 1 (3) ---> Task
27) Scenario B:
Suppose you have a four-activity sequential process. Throughput capacities in units per minute are shown in parentheses:
Task 1 (3) ---> Task 2 (4) ---> Task 3 (2) ---> Task 4 (5).
No buffers exist between tasks, so an upstream task must wait if the downstream task is busy.
What is the actual throughput rate for the sequential process as a whole (i.e., at what rate would units exit task 4)? Pick the closest answer
Group of answer choices
.5
1
2
3
4
5
28) Refer to Scenario B:
What would task 1's utilization be? Pick the closest answer.
Group of answer choices
0%
20%
40%
60%
80%
100%
29) Suppose you have a two-activity sequential process: Task 1 ---> Task 2.
Task 1 has a throughput capacity of 10 units per hour; task 2 has a throughput capacity of 15 units per hour. There are no inventory buffers between tasks.
Which of the following would be true?
Group of answer choices
Task 1 would encounter blocking
Task 2 would encounter blocking
Task 1 would encounter starvation
Task 2 would encounter starvation
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts