Question: Scenario C: Suppose you have a three task sequence. All customers go to Task A. After task A, 20% of customers go to Task B;
Scenario C:
Suppose you have a three task sequence. All customers go to Task A. After task A, 20% of customers go to Task B; the other 80% go to task C. After task B or C, all customers then go to Task D before leaving. There is an inventory buffer in between each station. Each buffer is empty at the start of each day.
Suppose throughput capacities are as follows. Task A: 30 customers/hour; task B: 10 customers/hour; task C: 20 customers/hour; task D, 32 customers/hour.
At what rate will customers leave task D (in customers/hour)? Pick the closest answer.
A.10
B.15
C.20
D.25
E.30
F.35
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts