Schedule Crashing Problem
Activity Normal Time Crash Time Normal Cost Crash Cost Time Difference Cost Difference Slope $/Day
A 21 $100
$2601 $160 $160/day
B 32 $200 $2401 $40 $40/day
C 42 $400
$5002 $100 $50/day
D 21 $300
$4501 $150 $150/day
E 42 $200 $3502 $150 $75/day
F 32 $250
$3501 $100 $100/day
G 11 $100
$100000