Question: Schedule performance index ( SPI ) less than one implies Project is behind schedule. Project performance is as per the baseline plan. Project is ahead

Schedule performance index (SPI) less than one implies
Project is behind schedule.
Project performance is as per the baseline plan.
Project is ahead of schedule.
Planned Value (PV) is less than Earned Value (EV).
 Schedule performance index (SPI) less than one implies Project is behind