Question: Schedule the following activities using CPM: A. Draw the network B. What is the critical path? C. How many weeks will it take to complete
Schedule the following activities using CPM:

A. Draw the network
B. What is the critical path?
C. How many weeks will it take to complete the project?
D. How much slack does activity B have?
\begin{tabular}{ccc} Activity & Immediate Predecessor & Time (weeks) \\ \hline A & - & 1 \\ B & A & 4 \\ C & A & 3 \\ D & B & 2 \\ E & C, D & 5 \\ F & D & 2 \\ G & F & 2 \\ H & E, G & 3 \\ \hline \end{tabular} \begin{tabular}{ccc} Activity & Immediate Predecessor & Time (weeks) \\ \hline A & - & 1 \\ B & A & 4 \\ C & A & 3 \\ D & B & 2 \\ E & C, D & 5 \\ F & D & 2 \\ G & F & 2 \\ H & E, G & 3 \\ \hline \end{tabular}