Question: Problem 4 - 8 ( Algo ) Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ]

Problem 4-8(Algo)
Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,3],[B,A,2],[C,A,5],[D,B,6],[E,C , D,2],[F,D,3],[G,F,5],[H,E,G,4]]
b. What is the critical path?
A-B-D-F-G-H
A-C-E-F-G-H
A-C-E-H
A-C-E-G-H
c. How many weeks will it take to complete the project?
Number of weeks