Question: Problem 4 - 8 ( Algo ) Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ]
Problem Algo
Schedule the following activities using CPM:
tableACTIVITYIMMEDIATE PREDECESSOR,TIME WEEKSABACADBEC DFDGFHE
b What is the critical path?
ABDFGH
ACEFGH
ACEH
c How many weeks will it take to complete the project?
Number of weeks