Question: Schedule the following activities using CPM: ACTIVITYIMMEDIATE PREDECESSORTIME ( WEEKS ) A 2 BA 5 CA 4 DB 3 EC % media:cm . png %

Schedule the following activities using CPM:
ACTIVITYIMMEDIATE PREDECESSORTIME (WEEKS)A2BA5CA4DB3EC%media:cm.png% D4FD1GF1HE%media:cm.png% G2
What is the critical path?
multiple choice 1
A-C-E-F-G-H
A-C-E-G-H