Question: Schedule the following activities using CPM: b. What is the critical path? A-B-D-E-HA-C-E-F-G-HA-C-E-G-HA-B-D-F-G-H0 c. How many weeks will it take to complete the project? c.

Schedule the following activities using CPM: b. What is the critical path? A-B-D-E-HA-C-E-F-G-HA-C-E-G-HA-B-D-F-G-H0 c. How many weeks will it take to complete the project? c. How many weeks will it take to complete the project? Answer is complete but nax entirely correct. d. Which activities have slack, and how much? B. 1 week; H,3 weeks; F, 2 weeks. B, 3 weeks; C, 1 week; F, 4 weeks. C. 4 weeks; F, 2 weeks; G, 2 weeks