Question: Schedule the following activities using CPM: b. What is the critical path? A-C-E-HA-B-D-E-HA-C-D-F-GA-B-D-F-G-H c. How many weeks will it take to complete the project? c.

Schedule the following activities using CPM: b.
Schedule the following activities using CPM: b.
Schedule the following activities using CPM: b. What is the critical path? A-C-E-HA-B-D-E-HA-C-D-F-GA-B-D-F-G-H c. How many weeks will it take to complete the project? c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B, 3 weeks; D, 1 week; and E,1 week. C. 3 weeks; F, 1 week; and G, 1 week. D, 2 weeks; G, 1 week; and H,1 week