Question: Schedule the following activities using CPM: b. What is the critical path? A-B-E-H A-B-D-E-H A-C-E-F-G-H A-B-D-F-G-H c. How many weeks will it take to complete

Schedule the following activities using CPM: b. What is the critical path? A-B-E-H A-B-D-E-H A-C-E-F-G-H A-B-D-F-G-H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B, 1 week; D, 3 weeks. E,1 week; H,2 weeks. C, 5 weeks; E, 2 weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
