Question: Schedule the following activities using CPM: TIME ACTIVITY IMMEDIATE PREDECESSOR (WEEKS) 2 A 5 A 6 B 3 C&media:cm.png% E 9 D F D 5

Schedule the following activities using CPM: TIME
Schedule the following activities using CPM: TIME ACTIVITY IMMEDIATE PREDECESSOR (WEEKS) 2 A 5 A 6 B 3 C&media:cm.png% E 9 D F D 5 G F 3 H E&media:cm.png% G 6 b. What is the critical path? OA-B-D-E-H O A-C-E-F-G-H OA-C-E-H OA-B-E-H c. How many weeks will it take to complete the project? Number of weeks ABCD De