Question: Schedule the following activities using CPM: 0 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) C&media:cm.png% Efmedia:cm.png% b. What is the critical path? A-B-D-E-H A-B-D-F-G-H A-C-E-G-H A-C-E-F-G-H c.

Schedule the following activities using CPM: 0

Schedule the following activities using CPM: 0 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) C&media:cm.png% Efmedia:cm.png% b. What is the critical path? A-B-D-E-H A-B-D-F-G-H A-C-E-G-H A-C-E-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? B. 3 weeks : C. 1 week: F. 4 weeks. B. 1 week ;H. 3 weeks ;F. 2 weeks. C.4 weeks ;F. 2 weeks : G. 2 weeks