Question: Schedule the following activities using the Critical Path Method: Activity, Immediate Processor, Time (Weeks) A, N/A, 1 B, A, 4 C, A, 3 D, B,

Schedule the following activities using the Critical Path Method:

Activity, Immediate Processor, Time (Weeks)

A, N/A, 1

B, A, 4

C, A, 3

D, B, 2

E, C and D, 5

F, D, 2

G, F, 2

H, E and G, 3

Question Set

a) Draw the network path.

b) What is the critical path?

c) How many weeks will it take to complete the project?

d) Which activities have slack, and how much?