Question: Schedule the process in such a way that every process gets minimum delay. There are 4 processes including interrupts whereas printer has the highest priority

Schedule the process in such a way that every process gets minimum delay. There are 4 processes including interrupts whereas printer has the highest priority as compared to User, 170, and disk Generating time of Printer User is T=Osee whereas printer observe a delay of 5 see after every 10sec of processing and requires 30sec to complete the task.User program ends at T=15sec I/O ends at 30sec disk ends at 45sec. Estimate the starting, ending processing time of each process and total time of whole process