Question: Schedule When will things be done? What is the milestone schedule? (A maximum of 12 milestones) The milestone schedule contains a maximum of 12 milestones

  1. Schedule

When will things be done?

  • What is the milestone schedule? (A maximum of 12 milestones)
  • The milestone schedule contains a maximum of 12 milestones and the due date for each milestone.
  • What is the completion time of the project?

Milestone Schedule

  • Start Date - February 2023
  • Land Survey/Inspections complete - April 2023 (5% budget)
  • First drawing sets issued for construction/tender - May 2023 (7.5-10% budget)
  • Drafted scopes of work ready for tendering - June 2023 (10-12.5% budget)
  • Permit for Construction - August 2023 (12.5-15% budget)
  • Shoring completed - October 2023 (25% budget)
  • Sub-grade waterproofing and footings completed - January 2024 (40% budget)
  • Building structure complete - May 2024 (60% budget)
  • Building envelope, glazing, and lido panels complete - September 2024 (75% budget)
  • Interior finishes to work in parallel floor-by-floor with glazing, complete - November 2024 (85% budget)
  • Deficiencies completed and occupancy permits approved - December 2024 (95% budget)
  • Project completion/occupancy move-in - January 2025 (100% budget)

(Make the schedule based on the information given under "milestone schedule")

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!