Question: Schedule When will things be done? What is the milestone schedule? (A maximum of 12 milestones) The milestone schedule contains a maximum of 12 milestones
- Schedule
When will things be done?
- What is the milestone schedule? (A maximum of 12 milestones)
- The milestone schedule contains a maximum of 12 milestones and the due date for each milestone.
- What is the completion time of the project?
Milestone Schedule
- Start Date - February 2023
- Land Survey/Inspections complete - April 2023 (5% budget)
- First drawing sets issued for construction/tender - May 2023 (7.5-10% budget)
- Drafted scopes of work ready for tendering - June 2023 (10-12.5% budget)
- Permit for Construction - August 2023 (12.5-15% budget)
- Shoring completed - October 2023 (25% budget)
- Sub-grade waterproofing and footings completed - January 2024 (40% budget)
- Building structure complete - May 2024 (60% budget)
- Building envelope, glazing, and lido panels complete - September 2024 (75% budget)
- Interior finishes to work in parallel floor-by-floor with glazing, complete - November 2024 (85% budget)
- Deficiencies completed and occupancy permits approved - December 2024 (95% budget)
- Project completion/occupancy move-in - January 2025 (100% budget)
(Make the schedule based on the information given under "milestone schedule")
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock