Question: Schedule-Cost-Resource The table below contains cost, resource, and schedule data for a hypothetical project. Questions: Create a network diagram for the tasks listed in the

  1. Schedule-Cost-Resource

The table below contains cost, resource, and schedule data for a hypothetical project.

 Schedule-Cost-Resource The table below contains cost, resource, and schedule data for

Questions:

  1. Create a network diagram for the tasks listed in the table above.
  2. Calculate earliest start, latest start, and float for each task.

Task

Earliest start (ES)

Latest start (LS)

Float

A

B

C

D

E

F

  1. Given the information captured in the network diagram, create a Gantt chart for the project. In the Gantt chart, picture weekends. (Assume the project begins on a Tuesday and that a week of effort is five working days long.)
  2. Calculate level of effort, labor costs, and total costs per task and put the values in the appropriate cells in the first table above.
  3. Assume the company being examined here has only two testers. How will this show up on a resource histogram? How should the work for Tasks D and E be leveled? What, if any, impact will the resource leveling have on the project duration?

Total cost Immediate predecessor Duration (weeks) Number of resources Level of effort* Labor cost Material cost $1,000 $2,000 2 designers @$1,600 per week per person 2 programmers @$1,200 per week per person 1 programmer @$1,200 per week $2,000 $5,000 1 testers @ $1,000 per week per person 2 tester @ $1,000 per week per person $2,000 DE 3 $1,000 2 integrators @ $1,800 per week per person Total $13,000 * Level of effort = number of workers x duration of work; e.g., 5 people working 3 days is equal to 15 person-days of effort. Total cost Immediate predecessor Duration (weeks) Number of resources Level of effort* Labor cost Material cost $1,000 $2,000 2 designers @$1,600 per week per person 2 programmers @$1,200 per week per person 1 programmer @$1,200 per week $2,000 $5,000 1 testers @ $1,000 per week per person 2 tester @ $1,000 per week per person $2,000 DE 3 $1,000 2 integrators @ $1,800 per week per person Total $13,000 * Level of effort = number of workers x duration of work; e.g., 5 people working 3 days is equal to 15 person-days of effort

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!