Question: Schedule-Cost-Resource The table below contains cost, resource, and schedule data for a hypothetical project. Questions: Create a network diagram for the tasks listed in the
- Schedule-Cost-Resource
The table below contains cost, resource, and schedule data for a hypothetical project.

Questions:
- Create a network diagram for the tasks listed in the table above.
- Calculate earliest start, latest start, and float for each task.
| Task | Earliest start (ES) | Latest start (LS) | Float |
| A | |||
| B | |||
| C | |||
| D | |||
| E | |||
| F |
- Given the information captured in the network diagram, create a Gantt chart for the project. In the Gantt chart, picture weekends. (Assume the project begins on a Tuesday and that a week of effort is five working days long.)
- Calculate level of effort, labor costs, and total costs per task and put the values in the appropriate cells in the first table above.
- Assume the company being examined here has only two testers. How will this show up on a resource histogram? How should the work for Tasks D and E be leveled? What, if any, impact will the resource leveling have on the project duration?
Total cost Immediate predecessor Duration (weeks) Number of resources Level of effort* Labor cost Material cost $1,000 $2,000 2 designers @$1,600 per week per person 2 programmers @$1,200 per week per person 1 programmer @$1,200 per week $2,000 $5,000 1 testers @ $1,000 per week per person 2 tester @ $1,000 per week per person $2,000 DE 3 $1,000 2 integrators @ $1,800 per week per person Total $13,000 * Level of effort = number of workers x duration of work; e.g., 5 people working 3 days is equal to 15 person-days of effort. Total cost Immediate predecessor Duration (weeks) Number of resources Level of effort* Labor cost Material cost $1,000 $2,000 2 designers @$1,600 per week per person 2 programmers @$1,200 per week per person 1 programmer @$1,200 per week $2,000 $5,000 1 testers @ $1,000 per week per person 2 tester @ $1,000 per week per person $2,000 DE 3 $1,000 2 integrators @ $1,800 per week per person Total $13,000 * Level of effort = number of workers x duration of work; e.g., 5 people working 3 days is equal to 15 person-days of effort
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
