Question: School administrators were complaining about a theme park across the street from the university which introduced a new ride, the Double Cyclone. The ride and
School administrators were complaining about a theme park across the street from the university which introduced a new ride, the Double Cyclone. The ride and queue have been causing a lot of commotion and noise to the detriment of university students. The ride holds 30 people in double roller coaster cars, and it takes 3.8 minutes to complete the ride circuit. It also takes the ride attendants another 3 minutes(with virtually no variation) to load and unload passengers. Passengers arrive at the ride during peak hours at a rate of 4 per minute, Poisson distributed. How many passengers were lined up waiting for the new ride?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts