Question: Scope change management: A project manager (PM) is overseeing a software development project. Midway through the project, a key stakeholder requests an additional feature that
Scope change management: A project manager (PM) is overseeing a software development project. Midway through the project, a key stakeholder requests an additional feature that was not part of the original scope. The PM agrees to add the feature without consulting the project team or evaluating the impact on the schedule and budget. How should the project manager have handled the stakeholders request?Question 16 options:Politely decline the request as it was not part of the original scopeAdd the feature and inform the team afterward to ensure rapid progressDocument the request and perform an impact analysis before making a decisionAgree to add the feature immediately to keep the stakeholder happy