Question: Scrum documents the work to be done during the sprint in . a. Product Backlog b. Requirement documentation c. WBS d. Sprint Backlog One of

Scrum documents the work to be done during the sprint in .

a.

Product Backlog

b.

Requirement documentation

c.

WBS

d.

Sprint Backlog

One of the following is not part of the project pre-initiation phase:

a.

Closing the project

b.

Determining the project constraints (time, scope..etc.)

c.

Select project manager

d.

Identify the project sponsor