Seasons Insaat constructs an office building under contract for the Cannon Company and uses the percentage-of-completion method.
Fantastic news! We've Found the answer you've been seeking!
Question:
- Seasons Insaat constructs an office building under contract for the Cannon Company and uses the percentage-of-completion method. The contract requires bills of progress and $1,550,000 paid quarterly. The total contract value is $18,600,000 and Seasons estimates the total cost to be $17,750,000. Seasons estimates the building will take 3 years to complete and begins construction on January 2, 2018. As of December 31, 2019, Seasons Construction estimates that 75% of the building has been completed; however, the total cost estimate due to unexpected price increases has increased to $18,000,000.
- What is the total amount of Construction Expenses that the seasons will recognize for the year ended 31 December 2019?
Related Book For
Intermediate Accounting
ISBN: 978-0324300987
10th Edition
Authors: Loren A Nikolai, D. Bazley and Jefferson P. Jones
Posted Date: