Question: SECTIM 1 3 . 2 - ACTIVITY DURATIONS Apyager is determining the activity durations for completing an instalin 5 5 0 lineal feet of 3

SECTIM 13.2-ACTIVITY DURATIONS
Apyager is determining the activity durations for completing an instalin 550 lineal feet of 358''10' high metal stud walls, installing g gypsum board to a level 5 finish. Using the PERT formula, determine
Optimistic time to install metal stud walls =16 days
Most likely time to install metal stud walls =25 days
Pessimistic time to install metal stud walls =28 days
PERT Formula: TE=(O+4M+P)6
TE=