Question: Section A Table 1 shows planned activities for a project designed to construct a new office block for the University of Zambia. ( 4 0
Section
Table shows planned activities for a project designed to construct a new office
block for the University of Zambia. Marks
Table : Planned Project Activities
Using the information provided in the table, do the following:
a Construct a network diagram precedence diagram Marks
b Compute forward pass and backward pass, marks
c Determine Float and Critical Path, and Marks
d Determine project duration. marks
Section B
Project time management includes all the processes required to ensure timely
completion of the project. Identify and explain the processes involved in project time
management. Using examples from a project of your choice real or imaginary
discuss the relevance of each process to ensuring timely completion of the project.
Marks
Write brief but scholarly notes on the following: Marks
a Cost Estimating, Marks
b Cost Budgeting and Marks
c Cost Control Marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock