Question: SECTION B [ 6 0 MARKS ] Answer ANY THREE ( 3 ) questions in this section. QUESTION 3 ( 2 0 Marks ) Using

SECTION B
[60 MARKS]
Answer ANY THREE (3) questions in this section.
QUESTION 3
(20 Marks)
Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible:
\table[[Task,Description,Duration,(Working Days),Predecessor/s],[A,Requirement Analysis,4,,-],[B,Systems Design,12,,A],[C,Programming,20,,B],[D,Telecoms,6,,B],[E,Hardware Installation,23,,B],[F,Integration,7,,C,D],[G,System Testing,13,,E,F],[H,Documentation,2,,G],[I,Training/Support,5,,H],[J,Handover and Go-Live,3,,H],[K,Maintenance,3,,I,J]]
3.1 Determine the critical path of the project.
(6 Marks)
3.2 Calculate the planned duration of the project in weeks.
(6 Marks)
3.3 Identify any non-critical tasks and the float (free slack) on each.
(8 Marks)
 SECTION B [60 MARKS] Answer ANY THREE (3) questions in this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!