Question: SECTION B [ 6 0 MARKS ] Answer ANY THREE ( 3 ) questions in this section. QUESTION 3 ( 2 0 Marks ) Using

SECTION B
[60 MARKS]
Answer ANY THREE (3) questions in this section.
QUESTION 3
(20 Marks)
Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible:
\table[[Task,Description,Duration,(Working Days),Predecessor/s],[A,Requirement Analysis,4,,-],[B,Systems Design,12,,A],[C,Programming,20,,B],[D,Telecoms,6,,B],[E,Hardware Installation,23,,B],[F,Integration,7,,C,D