Question: SECTION B [ 6 0 MARKS ] Answer ANY THREE ( 3 ) questions in this section. QUESTION 3 ( 2 0 Marks ) Using
SECTION B
MARKS
Answer ANY THREE questions in this section.
QUESTION
Marks
Using the information in the table below, assuming that the project team will work a standard working week working days in week and that all tasks will start as soon as possible:
tableTaskDescription,Duration,Working DaysPredecessorsARequirement Analysis,BSystems Design,ACProgramming,BDTelecoms,BEHardware Installation,BFIntegration,