Question: Section I - Numerical Calculations ( 5 0 % ) In a residential building project, a value engineering exercise was carried out on the roofing
Section I Numerical Calculations
In a residential building project, a value engineering exercise was carried out on the
roofing materials of the clubhouse. It is intended to revise the roofing materials from
composite aluminum roof cladding to thick. grade concrete flat roof
with greenery above.
a Advise the cost implication for the proposed change based on the rates and
assumptions provided below:
Assumptions:
Roof area:
Steel ratio:
All steel bar required are dia. and below
BQ Rates:
C wp reinforced concrete for suspended slabs; thk $
dia. and below bars; hot rolled deformed high yield $
Swan formwork to soffit of suspended slabs
Swan formwork; edges and breaks in slabs; ne
$
Design, supply and install roof greenery
$
Design, supply and install composite aluminum roof cladding
b After confirmation of adopting reinforced concrete roof with greenery features, the
Structural Engineer further advised that the rebar adopted was revised from
diameter to diameter. There is no relevant rates available for rebar
diameter over Assess the cost implication based on the following
assumptions:
Assumptions:
Wastage of rebar:
Profit and overhead of the contractor:
Cost of rebar all diameters:
Total bars required in :
Mass of rebar per linear meter:
Productivity for fixing rebar in different dia.
$tonne
same as the weight in a
mm
assume the same
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock