Question: See chapter 4 , page 1 0 2 , question 5 . The data for activities of the project is shown below: Activity Immediate Predecessor

See chapter 4, page 102, question 5. The data for activities of the project is shown below:
Activity
Immediate Predecessor
Time (weeks)
A
-
6
B
A
3
C
A
7
D
C
2
E
B, D
4
F
D
3
G
E, F
7
What is the minimum number of weeks needed to complete the project?