A group of five workstations produces a product. Answer the following questions using the input, output, and capability per hour data in the chart below.
- Calculate the number of units waiting at Workstations 2, 3, 4, and 5 after eight hours. Explain your answers.
- Which machine is the bottle-neck? Explain your answer.
|
| 1 | 2 | 3 | 4 | 5 |
| INPUT | 60 | 60 | 40 | 40 | 38 |
| CAPABILITY | 60 | 40 | 60 | 38 | 60 |
| OUTPUT | 60 | 40 | 40 | 38 | 38 |