Question: See the project task data in the table below. TAsk A, predeessor none, duration weeks 0; task b, predecessor A, duration weeks 10; task c,

See the project task data in the table below. TAsk A, predeessor none, duration weeks 0; task b, predecessor A, duration weeks 10; task c, predecessor a, duration weeks 20; task d, predecessor b,c, duration weeks 30 ; task e, predecessor b,c, duration weeks 20; task f, predecessor e, duration weeks 40; task g, predecessor d,f, duration weeks 20; task h, predecessor g, duration weeks 0; ; Determine the length (in weeks) of the four pathways from the start to the end of the project. What is the critical path, and thus what is the estimated duration of the project? Determine the task slack for each of the tasks of the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!