Question: Select all that apply correctly for the problem given below. Assume you have collected the following data for your project. Its budget is $75,000 and

Select all that apply correctly for the problem given below. Assume you have collected the following data for your project. Its budget is $75,000 and it is expected to last four months. After two months, you have the calculated the following information about the project: PV=$45,000EV=$38,000AC=$37,000 Select 3 correct answer(s) a) Project SPI=0.86 b) Project CPI=1.00 c) The project is behind schedule d) Estimate cost to completion is over $72,000