Question: Earned Value Exercise Exercise 1 Using the following data, calculate the planned and actual monthly budgets through the end of June. Assume the project is
Earned Value Exercise
Exercise 1
Using the following data, calculate the planned and actual monthly budgets through the end of June. Assume the project is planned for 12-month duration and a $250 000 budget.
| Activity | Jan | Feb | Mar | Apr | May | Jun | Plan | % Complete | Calc. Value* |
| Staffing | 8 | 7 | 15 | 100 | |||||
| Blueprinting | 4 | 6 | 10 | 100 | |||||
| Prototype Development | 2 | 8 | 10 | 70 | |||||
| Full Design | 3 | 8 | 10 | 21 | 67 | ||||
| Construction | 2 | 30 | 32 | 25 | |||||
| Transfer | 10 | 10 | 0 | ||||||
| Monthly Plan | |||||||||
| Cumulative | |||||||||
| Monthly Actual | 10 | 15 | 6 | 14 | 9 | 40 | |||
| Cumulative Actual |
*Calc. Value = product of Plan and % Complete (e.g. for Staffing, 15 x 1 = 15)
Using the data from the above table, calculate the following values:
| Schedule Variances | |
| Planned Value (PV) | |
| Earned Value (EV) | |
| Schedule Performance Index (SPI) | |
| Planned Time to Completion |
| Cost Variances | |
| Actual Cost of Work Performed (AC) | |
| Earned Value (EV) | |
| Cost Performance Index (CPI) | |
| Estimated Cost to Completion |
Exercise 2
You are calculating the estimated time to completion for a project of 1-year duration and a budgeted cost of $500 000. Assuming the following information, calculate the Schedule Performance Index (SPI) and the estimated time to completion.
| Schedule Variances | |
| Planned Value (PV) | 65 |
| Earned Value (EV) | 58 |
| Schedule Performance Index (SPI) | |
| Planned Time to Completion |
Exercise 3
Assume you have collected the following data for your project. Its budget is $75 000 and its expected to last 4 months. After 2 months, you have calculated the following information about the project:
PV = $45 000
EV = $38 500
AC = $37 000
Calculate SPI and CPI. Based on these values, estimate the time and budget necessary to complete the project. How would you evaluate these findings? Are they good news or bad news?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
