Question: Select all that apply Top down estimating for projects is best suited for situations when _ _ _ . fixed price contract used with an
Select all that apply
Top down estimating for projects is best suited for situations when
fixed price contract used with an external customer.
project proposals are being evaluated.
the project is for an external customer.
a WBS cannot easily be defined.