Question: Select all that apply Top down estimating for projects is best suited for situations when a WBS cannot easily be defined. project proposals are being
Select all that apply
Top down estimating for projects is best suited for situations when
a WBS cannot easily be defined.
project proposals are being evaluated.
the project is for an external customer.
fixed price contract used with an external customer.