Question: Select all the statements that are not true. Select 3 correct answer ( s ) The constant work - in - process ( ConWIP )

Select all the statements that are not true.
Select 3 correct answer(s)
The constant work-in-process (ConWIP) card aids input-output control by limiting the amount of work in a work centre.
Dispatching rules are typically judged by four effectiveness criteria: average completion time, utilization, average number of jobs in the system, and average job lateness.
The critical ratio sequencing rule prioritizes the jobs based on the importance or value of the customers who have placed the orders.
Earliest due date is a shop floor dispatching (sequencing) rule that relates the time available to complete a job to the amount of work left to be completed.
The assignment method provides an optimum, one-to-one assignment of resources to staff.
 Select all the statements that are not true. Select 3 correct

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!